Media Tour of North West projects has begun

The Renewed Hope Ambassadors’

First stop: The Abuja Kaduna road.

Section 1, 82 kilometers of concrete road measuring 200mm thick from Zuba junction to just after Jere, is nearly complete.

Contractors InfoQuest shared updates that the road project has reached almost completion and with only about 300 metres remaining and which should be finished in a matter of days.

Section 2, the 144 kilometer stretch inbound Kaduna, already has 15 kilometers completed. I was genuinely surprised by the scale of work done.

Officials from the Ministry of Works and InfoQuest engineers assured us at the Jere end that the road will be finished on schedule by November this year.

Special mention goes to Chukwuma Kalu, the resident engineer from the Federal Ministry of Works, who brilliantly broke down complex engineering terms into simple language for all of us.

I joined journalists, ministry representatives, and presidential aides to see President Tinubu’s road infrastructure for myself. Now we have seen some of the works and with a lot more of Tinubu’s infrastructural interventions to be seen, and inspected by us.

So far
So excell