FG gives Benin-Asaba concessionaire conditions to continue work


He said that while the road had been a difficult one that had transcended about three or four presidents, whatever palliative works the contractor carried out on the road were not professionally done.

The Federal Government of Nigeria, through the Minister of Works, Senator David Umahi, has given the Benin-Asaba Expressway Concession Company (BAECC) three distinct options on the way forward following widespread public outcry over the worsening condition and poor handling of the 125-kilometre highway project.

The Three Options Issued to BAECC at an emergency stakeholders’ meeting convened at the Edo State Government House in Benin City, the Minister presented the following conditions:

Bring in a Competent Contractor:
BAECC must partner with or hand over the actual construction to a technically and financially competent construction firm capable of meeting the required standards.

The Federal Government noted that three reputable contractors have already been identified to step in under this arrangement.

Execute a Tripartite Agreement:
Accept a restructured management arrangement involving a joint partnership between the Federal Government, the concessionaire, and an experienced third-party infrastructure firm to properly steer the engineering design and project execution.

Termination of the Concession:
Voluntarily surrender the concession agreement, allowing the Federal Government to revoke the contract fully and re-award it to an entirely new, capable company to alleviate the gridlock and complete the project.

Key Metrics & Project Timeline Project Attribute Details & Status

Project Extent125-kilometre corridor (reconstructed/expanded into a 10-lane highway).Initial Concession DateHanded over to BAECC in 2025.

Target Completion Date Originally scheduled for September 2027.

Current Progress StatusSeverely stalled; motorists were stranded for up to 5 days on failed sections before temporary stone filling occurred.

Financial Backing StructureInitially planned under a Public-Private Partnership (PPP) model funded via Africa Plus Partners, InfraCorp, and AAA Infrastructure.

Reasons Behind the Federal Government’s Ultimatum and Technical Incompetence:

The Ministry of Works accused BAECC of lacking the engineering capacity needed for a project of this magnitude.

Specifically, the company was heavily criticized for destroying public assets by stripping off existing asphalt layers without first building appropriate drainage infrastructure, leading to rapid deterioration during persistent rainfalls.

Severe Motorist Hardship:
Inaction and slow pace of work resulted in a massive structural failure of the highway, trapping heavy-duty vehicles and commuters for several days.

This sparked intense protests from local Edo youths and prompted a direct intervention order from President Bola Tinubu.

Nationwide Policy Shift:
The crisis has triggered a broader directives scheme from the Ministry of Works.

The Federal Government announced that it is launching a comprehensive review of all major road concession agreements across Nigeria to ensure financial viability and strict performance-based execution.